Saturday, October 27, 2007
Wednesday, October 24, 2007
Primer up
Sunday, October 21, 2007
HVAC Started
Friday, October 19, 2007
Mid October News
There hasn't been much activity at the house this week, hence not any new pictures since last week. Today the HVAC guy is out there though. Builder fixed the front fence as to secure the property tighter. We got 10 more sheets of hardi-plank delivered (still missing a few spots on the back and the carport side.... waiting for the guys to put that up to finish so we can paint. Next week the plumber should be out there so we need to decide on the shower trims so that we know what valves to have the plumber put in the walls. After he's done, the electrician comes out (that will take us going out there with him to pin point where we want everything). Inspections should follow. I can't wait for the drywall and paint so I can get my kitchen and bathrooms in there!! I'll update any pics if we have some this weekend of the HVAC, etc.
Sunday, October 14, 2007
More views of the backyard
Saturday, October 13, 2007
More siding, plywood on patio roof
Wednesday, October 10, 2007
Curb Cut
The city construction crew had to cut our curb, but unfortunately, they won't leave it that way. They'll put the curb back on (spend time and money on it) just so we can go in and cut it again in a couple of months. Oh well... green is not always green.
Hey- at least you can see a great view of the luxury mansion next to our house in this first shot!
Monday, October 8, 2007
Our Back Yard
Friday, October 5, 2007
View of the front and patio
Wednesday, October 3, 2007
News from Builder
The house has pretty much stayed the same for the last few days (and the city still has the street blocked off every other day or so). Builder gave us some news yesterday. Apparently, the plans for the egress windows were wrong and we need to knock out more space for the 3 lower windows in the bedrooms. They must be bigger to conform to code (I guess a large person must be able to escape them in a fire). So, they're figuring that out, getting the framers out again, and ordering different windows. They still haven't moved the long windows down (that are near the sliding glass doors) and that must be done before they'll put up the siding. The AC guy will be out next week, then the electrician (when he comes out, we need to go and meet him to give him very specific information), then the plumber. Builder said within 2.5 weeks, that all should be done. Then we go in and tell them what we want changed with the framing (knock out that door in the master bathroom, replace a few boards, etc). I'm assuming after all of that is changed, etc, we get inspectors out, play the waiting game a bit more, and then get it all approved (or not). I believe the next step from there is the foam insulation and then drywall/tape and float/painting, then kitchen and bathrooms, etc.
Oh- and were you wondering about the carport/patio roof? Builder finally called the company that was supposed to have delivered the T1-11 roof plywood weeks ago. They told him they delivered it. Builder said NO they didn't. Company said, YES we have pictures. They sent Builder the pictures only to find out they delivered it to the totally wrong site. Someone got a great deal there. So now they're back and forth about it and hopefully we'll get some more soon!! After that, the steel roof people will be out to put that on.
I'm assuming after all of that, we'll need the concrete people out again to pour the driveway. I'm not really sure what else I'm missing, but it's possible it will get done by Christmas now (although I probably shouldn't put that in writing--- I am knocking on wood now).
Oh- and were you wondering about the carport/patio roof? Builder finally called the company that was supposed to have delivered the T1-11 roof plywood weeks ago. They told him they delivered it. Builder said NO they didn't. Company said, YES we have pictures. They sent Builder the pictures only to find out they delivered it to the totally wrong site. Someone got a great deal there. So now they're back and forth about it and hopefully we'll get some more soon!! After that, the steel roof people will be out to put that on.
I'm assuming after all of that, we'll need the concrete people out again to pour the driveway. I'm not really sure what else I'm missing, but it's possible it will get done by Christmas now (although I probably shouldn't put that in writing--- I am knocking on wood now).